Electric Rates - Commercial and Industrial
Rates effective April 1, 2008
General Power GSA:
Part 1: For customers whose peak demand is less than 50 kW or energy less
than or equal to 15,000 kWh.
Customer Charge: $10.50 per meter
Energy Charge: 8.855¢ per kWh
Part 2: For customers
having a peak demand greater than 50 kW and less than or equal to 1,000
kW or energy greater than 15,000 kWh.
Customer Charge: $35 per meter
Demand Charge:
1st 50 kW: $0.00 per kW
All over 50kW: $11.78 per kW
Energy Charge:
1st 15,000 kWh: 8.889¢ per kWh
Over 15,000 kWh: 4.911¢ per kWh
Part 3: For customers
having a peak demand greater than 1,000 kW and less than or equal to 5,000
kW.
Customer Charge: $200 per meter
Demand Charge:
1st 1,000 kW: $11.52 per kW
All over 1,000 kW: $13.32 per kW
Energy Charge: 4.984¢ per kWh
General Power GSB:
For customers having a peak demand greater than 5,000 kW and less than
or equal to 15,000 kW.
Customer Charge: $1,500 per meter
Demand Charge: $13.17 per kW
Energy Charge:
Up to 620 kWh/kW: 4.234¢ per kWh
All over 620 kWh/kW: 3.559 ¢ per kWh
Facilities Charge:
Below 161 kV to 46 kV: $0.48 per kW
Below 46 kV:
1st 10,000 kW: $1.23 per kW
Excess over 10,000 kW: $0.97 per kW
General Power GSC:
For customers having a peak demand greater than 15,000 kW and less than
or equal to 25,000 kW.
Customer Charge: $1,500 per month
Demand Charge: 15,001 to 25,000 kW: $13.17 per kW
Energy Charge:
Up to 620 kWh/kW: 4.234¢ per kWh
All over 620 kWh/kW: 3.559¢ per kWh
Facilities Charge:
Below 161 kV to 46 kV: $0.48 per kW
Below 46 kV
1st 10,000 kW: $1.23 per kW
Excess over 10,000 kW: $0.97 per kW
General Power GSD:
For customers having a peak demand greater than 25,000 kW.
Customer Charge: $1,500 per month
Demand Charge: $16.23 per kW
Energy Charge: 3.507¢ per kWh
Facilities Charge: Below 161 kV to 46
kV: $0.48 per kW
Below 46 kV:
1st 10,000 kW: $1.23 per kW
Excess over 10,000 kW: $0.97 per kW
Electric Rates - Large Manufacturing
**Manufacturer Rates apply for over 5050 with
SIC CODES 20-39**
MANUFACTURER SERVICE MSB
Part 1: Applies to customers having a peak
demand less than 5,000 kW
Customer Charge: $1,500.00 per meter
Demand Charge: $11.28 per kW
Energy Charge:
First 620 kWh/kW: 3.689¢ per kWh
All over 620 kWh/kW: 3.113¢ per kWh
Part 2: Applies to customers having a peak
demand greater than 5,000 kW
Customer Charge: $1,500.00 per meter
Demand Charge: $10.67 per kW
Energy Charge:
First 620 kWh/kW: 3.531¢ per kWh
All over 620 kWh/kW: 2.988¢ per kWh
MANUFACTURER SERVICE MSC
Applies to customers alternating current, single
or three-phase, 60 hertz. Power delivered at a transmission voltage of
161 kV or if not available highest voltage available unless customer request
a lower standard voltage.
Customer Charge: $1,500.00 per meter
Demand Charge: $10.67 per kW
Energy Charge:
First 620 kWh/kW: 3.531¢ per kWh
All over 620 kWh/kW: 2.988¢ per kWh
MANUFACTURER SERVICE MSD
Applies to customers alternating current, single
or three-phase, 60 hertz. Power delivered at a transmission voltage of
161 kV or if not available highest voltage available unless customer request
a lower standard voltage.
Customer Charge: $1,500.00 per meter
Demand Charge: $13.17 per kW
Energy Charge: 2.943¢ per kWh
Outdoor Lighting LS:
Customer Charge:
Athletic Field and Traffic Signal Systems: $3.75 per meter
Energy Charge: 6.015¢ per kWh
Facilities Charge: 12 percent of installed
plant
Security Lighting Facility and Energy Charges:
(charge is per light per month)
175-watt MV (mercury vapor): $6.84
400-watt MV: $13.38
1,000-watt MV: $28.60
MV not available for new installations
100-watt HPS (high pressure sodium): $6.02
250-watt HPS: $11.21
400-watt: $16.86
Additional Monthly Pole
Charge
30-foot pole: $2.25
40-foot pole: $3.75
Special Floodlighting
Also Available
Electric Installation
Fees
For medium and larger developments, the Jackson Energy Authority will
provide the transformer and the underground feed to the transformer at
no cost if the customer provides the conduit and the transformer pad.
Electric Incentive Rates
Variable Price Interruptible (VPI): For customers with demands more than 5,000 kW. Power subject
to inturruption on 5 minute or 60 minute notice depending on option. Customer can contract up to
100% of total demand.
Demand charge: $1.21/kW
Energy charge: Varies by the hour
Flat Price Interruptible (FPI): For customers with demand more than 1,00 kW. Power subject to
interruption on 5 minute notice. Customer can contract up to 100% of total demand. Demand charge
credit of $3.40/kW.
Limited Interruptible
Power (LIP): For customers with demands of more than 20,000 kilowatts.
Customers can buy up to one half of their power requirements at the LIP
rate. There is a minimum of 24-hours notice and maximum of 15 days per
curtailment.
Demand Charge: $2.90 per kW
Energy Charge: $0.02004 per kWh
Limited Firm Power (LFP): Like LIP, this
program is for customers with demands of more than 20,000 kW. The curtailment
provisions also call for a minimum of 24-hours notice and a maximum of
15 days of curtailment. Customers, however, can buy up to 2/3 of their
power requirements at the LFP rate.
Demand Charge: $4.25 per kW
Energy Charge: $0.02004 per kWh
Electric Incentive Programs
Test and Restart Power (TRP): This program is for new and/or experimental
processes for existing industries and for restarting plants or processes
that have been idle for more than one year.
Minimum demand: 5,000 kW.
Power curtailed only during emergencies.
Available for up to 6 months.
Charges include monthly administrative charge
of $325, and energy priced at incremental cost of production, plus 25
percent. The energy charge is only on TRP; there is no demand charge.
The amount of demand taken above firm contract
is considered TRP. Time-differentiated metering is required.
Enhanced Growth Credit: This program gives a credit
of $6 per kW for four years to those who qualify in one of the following
three ways:
New or expanding customers in the standard industrial
classification groups of 20 to 39 for manufacturing and codes 40, 42,
44 and 45 for bulk transportation.
New or expanding commercial or industrial customers
that are all electric on heating, ventilation and air conditioning (HVAC),
have 50 percent of floor space heated and cooled, and have 50 percent
or more of the rated electric load represented by HVAC, interior lighting
and/or cooking.
Expanding customers who are adding at least 250
kW of electric load for all electric HVAC, water heating and/or cooking.
The minimum load requirement for SIC qualifiers
is 100 kW; the minimum for the other qualifiers is 250 kW.
|